We are pleased to share this construction update for Stages 1 & 2 at Octave, Junction Village.
On Stage 1, the subbase is now complete with the installation of kerb and channel significantly progressed. Gas and electrical connections are progressing well and will be completed in the coming weeks.
Works on the water and gas are underway on Stage 2, with kerb and channel set to commence in the coming weeks.
Check out this message from Jinding onsite:
With works progressing well, we are pleased to share that the current program anticipates titles for Stages 1 and 2 will be delivered Q2 2021. For more information please contact us at info@octave.zulu.nichestudio.biz.